Consider the following table of activities A through G in which A is the start node and G is the stop node. Activity Duration (days)

Consider the following table of activities A through G in which A is the start node and G is the stop node.

Activity Duration (days) Predecessor
A 5 --
B 8 A
C 7 A
D 6 A
E 9 B, C, D
F 10 B, C, D
G 5 E, F

On a piece of scratch paper, draw the network associated with this table and determine the following. What kind of activity is activity F?

a.

Burst activity

b.

Both critical activity and merge activity

c.

Merge activity

d.

Critical activity

e.

Non-critical activity

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these General Management questions

Question

=+ What are the subjects?

Answered: 1 week ago

Question

Explain the place of planning in human resource management

Answered: 1 week ago