Consider the following table of activities. Assume all activities require the same resource. Normal Activity Predecessors . Duration Assume the project is resource-constrained but not
Consider the following table of activities. Assume all activities require the same resource. Normal Activity Predecessors . Duration Assume the project is resource-constrained but not time-constrained. Assume only one resource is available at any time. Which activity should be started first? 1:" Activity B Activity C Activity D i' Both activities C and D ' Either activity B or activity D