Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Consider the following table of activities that describes a project network. How much reduction in project duration could you get from crashing activity C ?

Consider the following table of activities that describes a project network. How much reduction in project duration could you get from crashing activity C?
Project Activities
Activity
Predecessors
Normal
duration
(days)
Crash
duration
(days)
Normal cost
Crash cost
A
--
10
5
$
1,000
$
3,000
B
A
20
10
$
4,000
$
6,000
C
A
5
4
$
2,000
$
4,000
D
B, C
3
2
$
1,000
$
2,000
E
B, C
20
10
$
5,000
$
10,000
F
B, C
4
3
$
3,000
$
4,000
G
D, E, F
10
5
$
2,000
$
5,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management Achieving Competitive Advantage

Authors: Jeffrey K. Pinto

4th edition

133798070, 978-0133798074

More Books

Students also viewed these General Management questions

Question

2. Who regulates common carriers and how is it done?

Answered: 1 week ago

Question

3. How does a router differ from a layer-3 switch?

Answered: 1 week ago