Consider the following table of activities that describes a project network. Which activity will you crash first? Activity Predecessors Normal duration (days) Crash duration (days)
Consider the following table of activities that describes a project network. Which activity will you crash first?
Activity | Predecessors | Normal duration (days) | Crash duration (days) | Normal cost | Crash cost | |||||||||
A | -- | 10 | 5 | $ | 1,000 | $ | 3,000 | |||||||
B | A | 20 | 10 | $ | 4,000 | $ | 6,000 | |||||||
C | A | 5 | 4 | $ | 2,000 | $ | 4,000 | |||||||
D | B, C | 3 | 2 | $ | 1,000 | $ | 2,000 | |||||||
E | B, C | 20 | 10 | $ | 5,000 | $ | 10,000 | |||||||
F | B, C | 4 | 3 | $ | 3,000 | $ | 4,000 | |||||||
G | D, E, F | 10 | 5 | $ | 2,000 | $ | 5,000 | |||||||
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started