Question

1 Approved Answer

Consider the following table of activities that describes a project network. Which activity will you crash first? Activity Predecessors Normal duration (days) Crash duration (days)

Consider the following table of activities that describes a project network. Which activity will you crash first?

Activity

Predecessors

Normal duration (days)

Crash duration (days)

Normal cost

Crash cost

A

--

10

5

$

1,000

$

3,000

B

A

20

10

$

4,000

$

6,000

C

A

5

4

$

2,000

$

4,000

D

B, C

3

2

$

1,000

$

2,000

E

B, C

20

10

$

5,000

$

10,000

F

B, C

4

3

$

3,000

$

4,000

G

D, E, F

10

5

$

2,000

$

5,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Information Technology Project Management

Authors: Kathy Schwalbe

6th Edition

978-111122175, 1133172393, 9780324786927, 1111221758, 9781133172390, 324786921, 978-1133153726

More Books

Students also viewed these General Management questions