Consider the following tasks that must be assigned to four workers on a conveyor--paced assembly line (i.e., a machine--paced line flow). Each worker must perform
- Consider the following tasks that must be assigned to four workers on a conveyor--paced assembly line (i.e., a machine--paced line flow). Each worker must perform at least one task.
- Time to Complete Task (seconds):
- Task 1:26
- Task 2: 25
- Task 3: 15
- Task 4: 19
- Task 5: 15
- Task 6: 20
- Task 7: 49
- Task 8: 15
- Task 9: 20
- Task 10:25
- Task 11: 15
- Task 12: 20
- The current conveyor--paced assembly-line configuration assigns the workers in the following way:
- Worker 1: Tasks1, 2, 3
- Worker 2: Tasks 4, 5, 6
- Worker 3: Tasks 7, 8, 9
- Worker 4: Tasks 10, 11, 12
- Assume a demand rate of17 units per minute. What would be the target manpower?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started