Consider the following tasks, times, and predecessors for an assembly of set-top cable converter boxes: TASK ELEMENT TIME (MINUTES) PRECEDING TASKS A 8 B 8
Consider the following tasks, times, and predecessors for an assembly of set-top cable converter boxes:
TASK ELEMENT | TIME (MINUTES) | PRECEDING TASKS |
---|---|---|
A | 8 | |
B | 8 | A |
C | 9 | B |
D | 8 | B |
E | 10 | C, D |
F | 8 | A |
G | 8 | F |
H | 9 | G |
I | 8 | E, H |
Given a cycle time of 25 minutes, develop two alternative layouts. Use the longest task time rule and the largest number of following tasks as a secondary criterion. What is the highest efficiency of your layout, assuming the 25-minute cycle time?
Note: Enter your answer as a percentage rounded to 2 decimal places.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started