Consider the following three projects. Period Project A Project B Project C T=0 ($5,000) ($9,000) ($4,000) T=1 $2,000 $1,500 $900 T=2 $1,200 $2,500 $900 T=3
- Consider the following three projects.
Period Project A Project B Project C
T=0 ($5,000) ($9,000) ($4,000)
T=1 $2,000 $1,500 $900
T=2 $1,200 $2,500 $900
T=3 $1,800 $2,500 $200
T=4 $1,800 $2,500 $1,500
T=5 $1,800 $2,500 $1,500
When you have only $9,000 to support the above projects, which project (or projects) should be chosen under NPV method and explain WHY? Use 10 percent discount rate. (6 points)