Question

1 Approved Answer

Consider the following work breakdown structure: table [ [ , Start,Finish,Duration ( days ) ] , [ Activity , Node,Node,Optimistic,Most Likely,Pessimistic ] , [

Consider the following work breakdown structure:
\table[[,Start,Finish,Duration (days)],[Activity,Node,Node,Optimistic,Most Likely,Pessimistic],[A,1,2,41,50,59],[B,1,3,54,60,66],[C,2,4,58,70,82],[D,3,4,32,41,44]]
What is the estimated slack time for activity D?
Multiple Choice
79 days
20 days
19 days
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cases In Communications Law

Authors: Michael T Simpson, John Zelezny

6th Edition

1111791910, 9781111791919

More Books

Students also viewed these General Management questions