Question

1 Approved Answer

Consider the following work breakdown structure: table [ [ Activity , Precedes, table [ [ Duration Estimates ( Days ) ] , [

Consider the following work breakdown structure:
\table[[Activity,Precedes,\table[[Duration Estimates (Days)],[Optimistic]],Most Likely,Pessimistic],[Start,U,V,-,-,-],[U,W,35,50,65],[V,W,X,28,40,52],[W,Z,26,35,44],[X,Y,28,40,52],[Y,Z,26,29,38],[Z,End,36,60,84]]
What is the estimated expected (mean) time for project completion?
135 days
145 days
170 days
180 days
255 days
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management

Authors: William J Stevenson

12th edition

2900078024107, 78024102, 978-0078024108

More Books

Students also viewed these General Management questions