Consider the following work breakdown structure: table [ [ , , Time Estimates ( days ) ] , [ Activity , Precedes,Optimistic,Most Likely,Pessimistic, ]

Consider the following work breakdown structure:
\table[[,,Time Estimates (days)],[Activity,Precedes,Optimistic,Most Likely,Pessimistic,],[Start,A,B,-,-,-,],[A,C,D,44,50,56,],[B,D,45,60,75,],[C,E,42,45,48,],[D,F,31,40,49,],[E,F,27,36,39,],[F,End,58,70,82,]]
What is the estimated standard deviation in the time for activity E?
Multiple Choice
1 day
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management in Practice

Authors: Samuel J. Mantel Jr., Jack R. Meredith, Sco

4th edition

470533013, 978-0470533017

More Books

Students also viewed these General Management questions

Question

3) What are the characteristics of environment?

Answered: 1 week ago