Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J 15 10 8 K 9 8 7 L J 10
Consider the network described in the table below.
Activity | Immediate Predecessor(s) | Pessimistic | Probable | Optimistic |
J | 15 | 10 | 8 | |
K | 9 | 8 | 7 | |
L | J | 10 | 6 | 5 |
M | J | 3 | 3 | 3 |
N | K,M | 9 | 5 | 1 |
O | K,M | 10 | 7 | 4 |
P | L,N | 10 | 8 | 3 |
Draw the network diagram and answer the following questions. (a) Calculate the expected duration of each activity. (b) Calculate the expected duration and variance of the critical path. (c) Calculate the probability that the project will be completed in more than 28 time units
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started