Consider the project information in the following table. (time in days) Activity Predecessor Optimistic duration Normal duration Pessimistic duration A 5 6 7 B
Consider the project information in the following table. (time in days)
Activity | Predecessor | Optimistic duration | Normal duration | Pessimistic duration |
A | — | 5 | 6 | 7 |
B | — | 8 | 9 | 10 |
C | — | 1 | 3 | 5 |
D | C | 4 | 6 | 8 |
E | A | 2 | 3 | 4 |
F | B, D | 5 | 7 | 8 |
G | C | 6 | 8 | 9 |
a) Calculate the expected time, ES, EF, LS, LF, slack time and variance for each activity
b) What is the expected completion time of the project? Explain.
c) Estimate the probability of finishing the project in 15 days or less (showing calculation)
d) What is the project completion time so that there is a 95% probability that the project will be finished by this time?
Step by Step Solution
3.41 Rating (157 Votes )
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Document Format ( 2 attachments)
60d5e1d228932_227929.pdf
180 KBs PDF File
60d5e1d228932_227929.docx
120 KBs Word File
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started