Consider the project of developing an optical simulator which has 6 different tasks. The tasks and task times are provided below in the following table:
Consider the project of developing an optical simulator which has 6 different tasks. The tasks and task times are provided below in the following table:
Activity | Time | Immediate Predecessor |
A. Optical Design | 3 | - |
B. System Performance Analysis | 2 | A |
C. System Integration | 5 | A |
D. Cost Analysis | 2 | B, C |
E. Production Management | 6 | D |
F. Long Lead Item Procurement | 12 | D |
Using the information provided in the table, draw a network diagram using Arrow Diagramming Method (ADM).
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started