Consider the project with the following dependency matrix. Activity Predecessor Activity Times (Days) 1 2 2 1 5 3 2 7 4 2 3 5
Consider the project with the following dependency matrix.
Activity | Predecessor | Activity Times (Days) |
1 | 2 | |
2 | 1 | 5 |
3 | 2 | 7 |
4 | 2 | 3 |
5 | 2 | 4 |
6 | 4,5 | 6 |
7 | 3,6 | 3 |
8 | 6,7 | 8 |
a) Draw an activity network diagram and compute the earliest completion time of the project using EST/ECT.
b) Draw a Gantt chart for this project including slack times (Optional: utilize commercial software if possible).
Step by Step Solution
3.48 Rating (151 Votes )
There are 3 Steps involved in it
Step: 1
Lets start with part a drawing the activity network diagram a...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Information Technology Project Management
Authors: Kathy Schwalbe
9th Edition
1337101354, 978-1337101356
Students also viewed these General Management questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App