Consider the project with the following dependency matrix. Activity Predecessor Activity Times (Days) 1 2 2 1 5 3 2 7 4 2 3 5

Consider the project with the following dependency matrix.

ActivityPredecessorActivity Times (Days)
12
215
327
423
524
64,56
73,63
86,78

a) Draw an activity network diagram and compute the earliest completion time of the project using EST/ECT.

b) Draw a Gantt chart for this project including slack times (Optional: utilize commercial software if possible).

Step by Step Solution

3.48 Rating (151 Votes )

There are 3 Steps involved in it

Step: 1

Lets start with part a drawing the activity network diagram a... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Information Technology Project Management

Authors: Kathy Schwalbe

9th Edition

1337101354, 978-1337101356

More Books

Students also viewed these General Management questions

Question

Why do bars offer free peanuts?

Answered: 1 week ago