Consider the project with the following estimates for activity times and precedence relationships: table [ [ Activity , table [ [ Optimistic ]

Consider the project with the following estimates for activity times and precedence relationships:
\table[[Activity,\table[[Optimistic],[Time]],\table[[Most],[Likely Time]],\table[[Pessimistic],[Time]],\table[[Immediate],[Predecessor(s)]]],[A,3,4,5,-],[B,5,7,9,--],[C,2,3,10,A],[D,2,5,8,B],[E,1,7,7,B],[F,3,5,7,C, D],[G,7,8,9,D, E],[H,2,6,10,F]]
(a) What is the expected duration of the project?
(b) What is the project variance?
(c) If the deadline of the project is 25 days, what is the probability of finishing the project on time?
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Understanding And Managing Public Organizations

Authors: Hal G. Rainey, Sergio Fernandez, Deanna Malatesta

6th Edition

1119705894, 978-1119705895

More Books

Students also viewed these General Management questions

Question

5. If yes, then why?

Answered: 1 week ago

Question

6. How would you design your ideal position?

Answered: 1 week ago