Question

1 Approved Answer

Consider the scenario below.A contractor is forced to stop work on a building site owing to early heavy snowfall in late September. The force majeure

Consider the scenario below.A contractor is forced to stop work on a building site owing to early heavy snowfall in late September. The force majeure clause in the contract states the following:

Neither party shall be liable for damages related to the failure to perform the duties under this Agreement if such damages or failure to perform are related to conditions beyond the party's control including, but not limited to floods, tornadoes, fires, earthquakes, and other Acts of God, wars, insurrections, and/or any other cause beyond the reasonable control of the parties.

Could the contractor claim force majeure as grounds for more time?

Step 2

Post the following to the discussion board.Respond to the following and post your responses to the discussion board:

  • Summarize the case highlighting the relevant facts.
  • Document whether the contractor can claim more time. Why?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Law Express Evidence

Authors: Chris Taylor

5th Edition

1292210192, 978-1292210193

More Books

Students also viewed these Law questions

Question

Define in statistical control.

Answered: 1 week ago

Question

1. To take in the necessary information,

Answered: 1 week ago