Consider two projects: Project A currently costs $14 million, which is to be paid this year. The
Fantastic news! We've Found the answer you've been seeking!
Question:
Consider two projects: Project A currently costs $14 million, which is to be paid this year. The returns are $9 million in one year and $7 million in two years. Project B currently costs $11 million, again to be paid this year. The returns are $7 million in one year and $6 million in two years.
At an interest rate of 10%, the net present value of Project A is roughly , while the net present value of Project B is roughly .
Project A Options:
-0.03 million
0.54 million
-0.89 million
2.00 million
13.97 million
Project B Options:
0.32 million
0.81 million
1.22 million
2.00 million
11.32 million
Posted Date: