Question
1 Approved Answer
Consider two projects. The first project pays benefits of $85 today and nothing else. The second project pays nothing today, nothing one year from now,
Consider two projects. The first project pays benefits of $85 today and nothing else. The second project pays nothing today, nothing one year from now, but $104 two years from now.
a.Which project would be preferred if the discount rate were 0%?
b.What if the rate increased to 10%?
c.Find the Internal Rate of Return.