Question
1 Approved Answer
Construct the level plan that holds employment steady at 1,100 plus subcontracting (enter your responses as whole numbers). Level Plan Subcontract Ending Production Hire Quarter
Construct the level plan that holds employment steady at 1,100 plus subcontracting (enter your responses as whole numbers). Level Plan Subcontract Ending Production Hire Quarter Forecast Layoff (Units) Inventory (Units) (Units) 1,200 1 1,900 1,100 800 0 0 100 2 1,200 1,100 100 0 0 0 3 1,600 1,100 500 0 0 0 4 800 1,100 | 0 0 4