Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Construction Management Assignment on Financial Planning Fig. 1 (see overleaf) shows the AOA network of a construction project, with the precedence relationships and the activity

image text in transcribed

image text in transcribed

Construction Management Assignment on "Financial Planning" Fig. 1 (see overleaf) shows the AOA network of a construction project, with the precedence relationships and the activity durations indicated. The total costs of the different activities are summarized in the following table: Activity Total Cost ($) Duration (weeks) 1-2 2 4,800 2-3 10 16,000 2-4 10 18,000 2-5 8 16,800 3-6 6 15,000 4-6 4 8,000 4-7 17,600 8 5-7 6 15,600 6-8 6 16,200 7-8 5 10,500 8-9 6,900 3 The mark-up for the activities on the critical path is 15% and for the other activities is 10%. Progress measurements are made every four weeks with payments due four weeks later. 11% retention money is required for the project. The work on all the activities is to start at their earliest start times and to continue without delay. The value of work in progress is to be proportional to the time spent on it. the S-curve; the cumulative value vs. time curve; and (a) Draw: ii) ii) the cumulative income curve. (b) Draw the cash flow graph over the duration of the project. (c) Draw a graph of working capital vs. time (d) What is the total profit expected from the project? 5 6 5 9 8 10 7 2 2 6 10 6 6 3 Figure 1. AOA Network Diagram co Construction Management Assignment on "Financial Planning" Fig. 1 (see overleaf) shows the AOA network of a construction project, with the precedence relationships and the activity durations indicated. The total costs of the different activities are summarized in the following table: Activity Total Cost ($) Duration (weeks) 1-2 2 4,800 2-3 10 16,000 2-4 10 18,000 2-5 8 16,800 3-6 6 15,000 4-6 4 8,000 4-7 17,600 8 5-7 6 15,600 6-8 6 16,200 7-8 5 10,500 8-9 6,900 3 The mark-up for the activities on the critical path is 15% and for the other activities is 10%. Progress measurements are made every four weeks with payments due four weeks later. 11% retention money is required for the project. The work on all the activities is to start at their earliest start times and to continue without delay. The value of work in progress is to be proportional to the time spent on it. the S-curve; the cumulative value vs. time curve; and (a) Draw: ii) ii) the cumulative income curve. (b) Draw the cash flow graph over the duration of the project. (c) Draw a graph of working capital vs. time (d) What is the total profit expected from the project? 5 6 5 9 8 10 7 2 2 6 10 6 6 3 Figure 1. AOA Network Diagram co

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial management theory and practice

Authors: Eugene F. Brigham and Michael C. Ehrhardt

12th Edition

978-0030243998, 30243998, 324422695, 978-0324422696

More Books

Students also viewed these Finance questions