Consuelo Chun Inc. is a disk drive manufacturer in need of an aggregate plan for July through December The company has gathered following data Costs

Consuelo Chun Inc. is a disk drive manufacturer in need of an aggregate plan for July through December The company has gathered following data
Costs
Holding cost $8/disk/month
subcontracting $80/disk
Regular labor time $12/hour
Overtime labor $18/hour for hours about 8/hours/worker/day
Hiring cost $40/worker
Layoff cost $80/worker
demand
July 400
August 500
September 550
October 700
November 800
december 700
Note-No cost-incurred for unmet demand but unmet demand (backorder) must be handled in the following period it half or more worker is needed, round up
Other data
Current workforce 8 people
Labor hour/disk 4 hours
Workdays/month 20 days
beginning inventory 150 disks
No / requirement for ending inventor 0 disks
( No holiday cost for June)
What will be costing of two following strategies
1. Vary work force so that production meets demand 8 was workers on board in June
2. Vary overtime only and use constant workforce of eight.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials Of Management

Authors: Andrew J DuBrin

10th Edition

0996757872, 9780996757874

More Books

Students also viewed these General Management questions