Contract No.12476 commenced during year 2017 and has a fixed contract price of RM900,000. During the year 2017, costs incurred for materials, wages and

 

Contract No.12476 commenced during year 2017 and has a fixed contract price of RM900,000. During the year 2017, costs incurred for materials, wages and sub-contractors charges amounted to RM420,000. A plant costing RM78,000 was purchased during year 2017 specifically for contract No.12476. At the end of year 2017: i. The plant was valued at RM62,000. ii. Unused materials on site were valued at RM80,000. It is estimated that further costs recognise RM290,000 would be incurred in order to complete the contract. The figure includes the appropriate cost of plant and sub- ii. contractors in the future. iv. The progress billing was RM388,800. Required: a) Prepare the following: i. Extract of the Statement of Profit or Loss for the year of 2017. Extract of Statement of Financial Position for the year of 2017, assuming the entity recognised revenue based on cost to date bears to total cost. ii. (13 marks) b) Prepare the following: i. Extract of the Statement of Profit or Loss for the year of 2017. Extract of the Statement of Financial Position for the year of 2017, assuming the ii. entity recognised revenue on the basis of value of work certified. The progress billing represents 90% of work invoiced.

Step by Step Solution

3.51 Rating (151 Votes )

There are 3 Steps involved in it

Step: 1

Contract no12476 Total contract value 900000 Statement of Profit or loss for the year 2017 Costs i... blur-text-image
Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Federal Taxation 2018 Comprehensive

Authors: Thomas R. Pope, Timothy J. Rupert, Kenneth E. Anderson

31st Edition

134532384, 978-0134550893, 134550897, 978-0134532387

More Books

Students explore these related General Management questions

Question

As the internal transfer price is increased

Answered: 3 weeks ago