Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Content x o Mail - Md Sadikur Rahman Shim X Content X Zoom Virtual Classroom - Zoom X learn.senecacollege.ca/ultra/courses/_664382_1/cl/outline V O X Learning Resources X
Content x o Mail - Md Sadikur Rahman Shim X Content X Zoom Virtual Classroom - Zoom X learn.senecacollege.ca/ultra/courses/_664382_1/cl/outline V O X Learning Resources X Course Outline Remaining Time: 50 minutes, 31 seconds. Seneca Resources Question Completion Status: Common Tips 10 21 30 40 50 60 7 80 90 10 11 125 Email Question 10 10 points Save Answer My Groups During planning, your team has identified the items in the following table as work to be done on the project. Draw a network diagram to graphically depict this flow. All relationships are F-S relationships and duration are in days. Project Assignment 1 1 Task Duration Predecessor Start M U O E 4 F 4 G H X Waiting for cache. 15.C Mostly cloudy Based on the network diagram, on which tasks would you consider applying a Lead? Note: Leads are used when there is a successor task that can begin before the predecessor is complete. You can also apply leads to shorten the project schedule. D HOMI O a. You do not have enough information to answer this question. Ob. You would need to analyze the impact on each task and the project schedule. O c. Tasks | and L O d. Task K Question 10 of 12 10:35 PM ENG 2022-06-17 A Moving to another question will save this response. PO N O X 15 C Mostly cloudyontent X Mail - Md Sadikur Rahman Shim X Content x Zoom Virtual Classroom - Zoom X + C learn.senecacollege.ca/ultra/courses/_664382_1/cl/outline V - X Learning Resources QEX AIM : Course Outline Remaining Time: 50 minutes, 06 seconds. Seneca Resources Question Completion Status: Common Tips 10 20 36 40 50 61 76 80 9 10 11 120 Z Moving to another question will save this response. Email K Question 3 12 points saved My Groups During planning, your team has identified the items in the following table as work to be done on the project. Draw a network diagram to graphically depict this flow. All Project Assignment 1 1 relationships are F-S relationships and duration are in days. Task Duration Predecessor A Start D E 3 1 4 m MUC F 4 G 8 1 1 4 G K 1S'C M 123 Mostly cloudy N Based on the network diagram, on which tasks might you consider adding additional resources if you need to shorten the schedule? P HOM O a. Task C b. Task D c. Task B Od. Task C and D | Question 3 of 12 8 10:36 PM 4 2022-06-17 > Moving to another question will save this response. 15 C Mostly cloudy acer D . 1080-2 ... sources Remaining Time: 59 minutes, 22 seconds. Question Completion Status: Tips Question 1 12 points Saved ups During planning, your team has identified the items in the following table as work to be done on the project. Draw a network diagram to graphically depict this flow. All relationships are F-S relationships and duration are in days. ssignment 1 1 T Task Duration Predecessor start N M H M + 0O H H OO H N L, M Based on the network diagram, which statement is most true? D' HD O] a. Task I must be completed before task N can begin. O b. Tasks L and M must be completed before task N can begin. O c. Tasks E and F must be completed before task N can begin. Od. Task J must be completed before task N can begin. Question 1 of 12 10:27 PM 2022-06-17 Moving to another question will save this response. Z O Q y cloudyZoom Virtual Classroom - Zoom X 664382_1/cl/outline X IM Remaining Time: 50 minutes, 40 seconds. Question Completion Status: 10 20 30 4 50 60 8 9 10 11 125 Question 11 12 points Save Answer During planning, your team has identified the items in the following table as work to be done on the project. Draw a network diagram to graphically depict this flow. All relationships are F-S relationships and duration are in days. Task Duration Predecessor Start 1 4 4 0 m UO -Y - EZ 1S'G Mostly cloud Based on the network diagram, which answer is correct? D Hom a. A-B-E-I-L-N is the critical path O b. A-C-G-J-M-N is the critical path c. A-B-F-I-L-N is the critical path Old. A-D-H-K-M-N is the critical path Question 11 of 12 Moving to another question will save this response. 10:35 PM ENG 2022 04:17 US PX Remaining Time: 58 minutes, 57 seconds. Question Completion Status: Question 2 12 points Save Answer During planning, your team has identified the items in the following table as work to be done on the project. Draw a network diagram to graphically depict this flow. All relationships are F-S relationships and duration are in days. Task Duration Predecessor Start I M U Q W LO I - - Y - EZ 4 Mostly cloudy Based on the network diagram, which task has the most float? Ham O a. Task E O b. Task B O c. Task L O d. Task I X Question 2 of 12 2022-06-17 Moving to another question will save this response. Z X
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started