Contract #1482 began on April 1, 2012. As of December 31, 2012, the end of the contractors accounting year, costs incurred were as follows: $

Contract #1482 began on April 1, 2012. As of December 31, 2012, the end of the contractor’s accounting year, costs incurred were as follows:

$

Materials issued 480,000

Materials on site, December 31, 2012, 40,000

Labour 720,000

The plant issued to the site on April 1, 2012, 800,000

Written down value of plant December 31, 2012, 560,000

Overheads 120,000

The contract is expected to end in March 2013 and as at December 31, 2012 the cost accountant estimated that the final cost of the contract would be $1,900,000. The full contract price is $1,800,000. Work certified as at December 31, 2012 was valued at $1,400,000. The contractee made progress payments of $1,260,000 up to December 31, 2012.

Required:

  1. Prepare the Contract Account. 
  2. Prepare the contract P&L account
  3. Prepare the Contractee Account. 
  4. Calculate the Balance Sheet value of work-in-progress as at December 31, 2012. 
  5. List the items that would be included in the contractor’s Balance Sheet on December 31, 2012. 

Step by Step Solution

3.32 Rating (149 Votes )

There are 3 Steps involved in it

Step: 1

a Prepare the Contract Account 10 marks Dr Contract Account 2012 Details Dec 31 Materials issued Lab... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Federal Income Taxation In Canada

Authors: Robert E. Beam, Stanley N. Laiken, James J. Barnett

33rd Edition

1554965020, 978-1554965021

More Books

Students also viewed these Accounting questions