Contract BD258 began on January 15, 2020 and was completed on September 15, 2020 in the contractors financial year. The total value of the contract
Contract BD258 began on January 15, 2020 and was completed on September 15, 2020 in the contractors financial year. The total value of the contract was $6,500 000. On December 31, 2020, the inspecting engineer issued his final certificate of work done. The following information relating to the contract was made available from the companys records:
Details/Accounts | $ |
Direct labour | 1,200,000 |
Direct materials, less returns | 480,000 |
Materials from store and workshops | 196,000 |
Plant maintenance and use | 380,000 |
Direct expenses | 400,000 |
General overheads | 240,000 |
Materials on hand December 31st | 40,000 |
Wages owing at December 31st | 65,000 |
Direct expenses prepaid | 48,000 |
Value of work certified by the inspecting engineer | 4,000,000 |
Cash received on account | 4,500,000 |
Required:
- Prepare the contract BD258 account as at December 31st 2020. (15 marks)
- Prepare the contract P&L account for the year ended December 31st 2020. (5 marks)
- Prepare the Contractee Account as at December 31st, 2020. (5 marks)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started