Question
1 Approved Answer
Contract price is P5 500 000, total cost to date is P2 000 000, Value of work certified to date is P1 500 000, what
Contract price is P5 500 000, total cost to date is P2 000 000, Value of work certified to date is P1 500 000, what is the stage of completion of the contract? a 27.27% b 36.36% c 75% d 63.63%.