Question
1 Approved Answer
Contractor has substantially completed a $2 million project. The punch list indicates the estimate of the deficient work as $200,000 . Per the contract, the
Contractor has substantially completed a $2 million project. The punch list indicates the estimate of the deficient work as $200,000 . Per the contract, the retainage is 5% for closeout items and 1.5