contractor started a work from 1st January 2020. On 1st March 2020, a plant costing Rs. 80,000 was purchased for the contract. A part of
contractor started a work from 1st January 2020. On 1st March 2020, a plant costing
Rs. 80,000 was purchased for the contract. A part of the plant costing Rs. 8,000 was
unsuitable and returned to store on 31st May 2010. Plant costing Rs. 6,000 was stolen from
the site at the beginning. Plant costing Rs. 20,000 was sold for Rs. 13,000 on 31st December
2020. Accounts are closed on 31st December every year. Charge depreciation 10% per
annum and show the treatment of plant in the contract account treating it as a long-term
contract.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Treatment of Plant in the Contract Account LongTerm Contract Information Contract started January 1st 2020 Plant purchased March 1st 2020 Rs 80000 Plant returned May 31st 2020 Rs 8000 Plant stolen Beg...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started