Question
1 Approved Answer
Cook Contractors is a general construction company with a wide variety of projects. Budgeted and actual (to date) results (in thousands of dollars) for a
Cook Contractors is a general construction company with a wide variety of projects. Budgeted and actual (to date) results (in thousands of dollars) for a building project follow.
Budget | Actual | |||||||||||||
Month | Cost | %Complete | Cost | %Complete | ||||||||||
0 | $ | 0 | 0.0 | % | $ | 0 | 0.0 | % | ||||||
1 | $ | 820 | 2.8 | % | $ | 1,010 | 2.5 | % | ||||||
2 | $ | 1,640 | 5.6 | % | $ | 1,720 | 5.5 | % | ||||||
3 | $ | 2,460 | 8.4 | % | $ | 2,390 | 7.2 | % | ||||||
4 | $ | 3,280 | 11.2 | % | $ | 3,300 | 10.9 | % | ||||||
5 | $ | 4,100 | 14.0 | % | $ | 4,150 | 13.5 | % | ||||||
6 | $ | 4,920 | 16.8 | % | $ | 5,050 | 17.0 | % | ||||||
7 | $ | 5,740 | 19.6 | % | $ | 5,800 | 19.5 | % | ||||||
8 | $ | 6,560 | 22.4 | % | $ | 6,640 | 21.8 | % | ||||||
9 | $ | 7,380 | 25.2 | % | $ | 7,870 | 23.5 | % | ||||||
10 | $ | 8,200 | 28.0 | % | $ | 8,410 | 24.9 | % | ||||||
11 | $ | 9,020 | 30.8 | % | $ | 9,390 | 25.0 | % | ||||||
12 | $ | 9,840 | 33.6 | % | $ | 10,010 | 28.0 | % | ||||||
13 | $ | 10,660 | 36.4 | % | ||||||||||
14 | $ | 11,480 | 39.2 | % | ||||||||||
15 | $ | 12,300 | 42.0 | % | ||||||||||
16 | $ | 13,120 | 45.2 | % | ||||||||||
17 | $ | 13,940 | 48.4 | % | ||||||||||
18 | $ | 14,760 | 51.6 | % | ||||||||||
19 | $ | 15,580 | 54.8 | % | ||||||||||
20 | $ | 16,400 | 58.0 | % | ||||||||||
21 | $ | 17,220 | 61.2 | % | ||||||||||
22 | $ | 18,040 | 64.4 | % | ||||||||||
23 | $ | 18,860 | 67.6 | % | ||||||||||
24 | $ | 19,680 | 70.8 | % | ||||||||||
25 | $ | 20,500 | 74.0 | % | ||||||||||
26 | $ | 21,320 | 79.2 | % | ||||||||||
27 | $ | 22,140 | 84.4 | % | ||||||||||
28 | $ | 22,960 | 89.6 | % | ||||||||||
29 | $ | 23,780 | 94.8 | % | ||||||||||
30 | $ | 24,600 | 100.0 | % | ||||||||||
Required:
a. At this time, what is the current cost over (under) run on the project? (Enter your answer in dollars and not in thousands of dollars.)
b. At this time, by how far ahead or behind schedule is the project in terms of percentage of completion? (Round your answer to 1 decimal place.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started