Cooper Manufacturing is currently working on two jobs. The job order cost sheets for Job 101 and Job 102 showed the following information: Direct
Cooper Manufacturing is currently working on two jobs. The job order cost sheets for Job 101 and Job 102 showed the following information: Direct Materials Direct labor Job 101 $19,000 31,000 Job 102 $22,000 52,000 If overhead is applied to jobs at $0.60 per direct labor dollar, the overhead applied to the two jobs would be: