Question
Corey is considering the following two projects. He requires a 18 percent rate of return for both projects. Time (year) 0 1 2 3 4
Corey is considering the following two projects. He requires a 18 percent rate of return for both projects.
Time (year) | 0 | 1 | 2 | 3 | 4 | 5 |
Project A | -1850 | 540 | 550 | 720 | 770 | 810 |
Project B | -2170 | 660 | 630 | 810 | 890 | 900 |
Answer the following questions related to these projects. Do not include the $ or % sign in answers.
(a) Find the IRR for project A as a % expressed to 2 decimal places
(b) Find the NPV for project A expressed to 2 decimal places
(c) At what required rate of return would the NPV of both projects be equal? Express answer as a percent to 2 decimal places
(d) If the two projects A and B are mutually exclusive which project should be chosen? Pick A or B
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3