Question
cornerstones 3rd eddition by Hansen, Don R problem #2 Sparingly Manufacturing has developled the following standards for one of its products. STANDARD VARIABLE COST CARD
cornerstones 3rd eddition by Hansen, Don R
problem #2
Sparingly Manufacturing has developled the following standards for one of its products.
STANDARD VARIABLE COST CARD (One Unit of Product)
Material: 5yards x $6 per yard $30.00
Direct labor: 2hours x $8 per hour 16.00
Variable manufacturing overhead: 2 hours x $5 per hour 10.00
Total standard variable cost per unit 56.00
The company records materials price variances at the time of purchase.
The following activity occurred during the month of December:
Materials purchased: 5,200 yards costing $29,900
Materials used: 4,750 yards
Units produced: 1,000 units
Direct labor: 2,100 hours costing $17,850
Required:
a. calculate the direct materials price variance.
b. calculate the direct materials usage variance.
c. calculate the direct labor rate variance.
d. calculate the direct labor efficiency variance.
thank you in advance for your help.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started