Coronado Industries is constructing a building. Construction began in 2020 and the building was completed 12/31/20. Coronado made payments to the construction company of $3018000
Coronado Industries is constructing a building. Construction began in 2020 and the building was completed 12/31/20. Coronado made payments to the construction company of $3018000 on 7/1, $6264000 on 9/1, and $5940000 on 12/31. Weighted-average accumulated expenditures were
| $3597000. |
| $9282000. |
| $15222000. |
| $3075000. |