Cost and Management Accounting Intermediate Pres.JI A worker is allowed 1 0 hours to complete a job on daily wages. He takes 6 hours to

Cost and Management Accounting
Intermediate
Pres.JI A worker is allowed 10 hours to complete a job on daily wages. He takes 6 hours to complete the job under a scheme of payment by results. His day rate is 6 per hour and piece rate is 36. The material cost of the product is 40 and the overheads are charged at 150% of the total direct wages. Calculate the factory cost of the product under -
(i) Piece Work Plan:
(ii) Rowan Plan; and
(iii) Halsey Plan.
[Ans.130; (ii)166; (c)160.]
{CS (Inter) Dec. 1998}
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting For MBAs

Authors: Peter Easton, Robert Halsey, Mary Lea McAnally, John Wild

8th Edition

1618533584, 9781618533586

More Books

Students also viewed these Accounting questions

Question

How did the authors avoid the post hoc fallacy?

Answered: 1 week ago

Question

Appreciate the importance of developing potential managers

Answered: 1 week ago

Question

Know how to approach on-the-job training

Answered: 1 week ago