Cost Code Date 06-1100M Description Variance Rough Carpentry Materials $5,000 Budget $95,000 Committed $90,000 Review the above example from a job cost report. You have
Cost Code Date 06-1100M Description Variance Rough Carpentry Materials $5,000 Budget $95,000 Committed $90,000 Review the above example from a job cost report. You have just completed the "buyout" or purchasing phase of the project. Describe what the above means to you. Cost to $0