Question
1 Approved Answer
Cost Code Variance 03-3100M ($25,000) Description A. ($25,000) B. ($7,500) C. ($8,750) D. ($33,750) Concrete Material Budget $150,000 Committed $175,000 Cost to Date $135,000 The
Cost Code Variance 03-3100M ($25,000) Description A. ($25,000) B. ($7,500) C. ($8,750) D. ($33,750) Concrete Material Budget $150,000 Committed $175,000 Cost to Date $135,000 The current project schedule update tells us that the concrete scope of work is 72% poured/placed. In the same example as the previous question, how much cost over budget can we anticipate for the concrete material line item? (i.e. what is the total "hit" we are going to take on this cost code?) The current project schedule update tells us that the concrete scope of work is 72% poured/placed. In the same example as the previous question, how much cost over budget can we anticipate for the concrete material line item? (i.e. what is the total "hit" we are going to take on this cost code?) A. ($25,000) B. ($7,500) C. ($8,750) D. ($33,750)
Cost Code Variance 03-3100M ($25,000) Description A. ($25,000) B. ($7,500) C. ($8,750) D. ($33,750) Concrete Material Budget $150,000 Committed $175,000 Cost to Date $135,000 The current project schedule update tells us that the concrete scope of work is 72% poured/placed. In the same example as the previous question, how much cost over budget can we anticipate for the concrete material line item? (i.e. what is the total "hit" we are going to take on this cost code?)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started