Cost of project A at the beginning of project is 60,000$. Benefits of 100,000$ occur in the second year. Assume that discount rate is 3%,
Cost of project A at the beginning of project is 60,000$. Benefits of 100,000$ occur in the second year. Assume that discount rate is 3%, what is the net benefit of this project? A. 100,000$ B. 40,000$ C. 37,087$ D.34,260 \$