Question
Cost Pool Estimated Overhead Maintenance $40,000 Setup $20,000 Quality Control $30,000 Ordering & Receiving $50,000 Expected Activity Desks Tables Chairs Total Machine Hours 500 200
Cost Pool | Estimated Overhead | |||
Maintenance | $40,000 | |||
Setup | $20,000 | |||
Quality Control | $30,000 | |||
Ordering & Receiving | $50,000 | |||
Expected Activity | Desks | Tables | Chairs | Total |
Machine Hours | 500 | 200 | 300 | 1,000 |
Batches | 25 | 35 | 20 | 80 |
Inspections | 60 | 10 | 30 | 100 |
Purchase Orders | 25 | 10 | 15 | 50 |
Units | 800 | 650 | 2,000 | 3,450 |
Budget Data | Desks | Tables | Chairs | Total |
Sales | $250,000 | $240,000 | $220,000 | $710,000 |
Direct Materials | $50,000 | $60,000 | $45,000 | $155,000 |
Direct Labor | $30,000 | $35,000 | $25,000 | $90,000 |
How much does it cost to make one table using the ABC method (what is the total cost per unit)?
Group of answer choices
$189.23
None of these answers are correct.
$361.54
$229.91
$191.92
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started