Could you help me with the following EANB problem? Question There are two projects under consideration: Project A has an NPV of $20m and will
Could you help me with the following EANB problem?
Question
There are two projects under consideration:
Project A has an NPV of $20m and will last three years.
Project B has an NPV of $60m and will last nine years.
It is anticipated that if either project is chosen it will be possible to repeat it for the foreseeable future. The interest rate is 1% per year. Which project will have a higher EANB and why?