Question
Cox Engineering performs cement core tests in its laboratory. The following standards have been set for each core test performed: Standard Hours or Quantity. Standard
Cox Engineering performs cement core tests in its laboratory. The following standards have been set for each core test performed:
Standard Hours or Quantity. Standard Price or Rate
Direct materials 3.0 pounds 0.75 per pound
Direct labour 0.4 hours 12.00 per hour
Variable manufacturing overhead 0.4 hours 9.00 per hour
During March, the laboratory performed 2,000 core tests. On March 1 no direct materials (sand) were on hand. Variable manufacturing overhead is assigned to core tests on the basis of direct labour hours. The following events occurred during March:
8,600 pounds of sand were purchased at a cost of 7,310.
7,200 pounds of sand were used for core tests.
840 actual direct labour hours were worked at a cost of 8,610.
Actual variable manufacturing overhead incurred was 3,200.
The labour efficiency variance for March is:
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started