Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Cox Engineering performs cement core tests in its laboratory. The following standards have been set for each core test performed: Standard Hours or Quantity Standard

Cox Engineering performs cement core tests in its laboratory. The following standards have been set for each core test performed:

Standard Hours or Quantity Standard Price or Rate

Direct materials 3.0 pounds 0.75 per pound

Direct labour 0.4 hours 12.00 per hour

Variable manufacturing overhead 0.4 hours 9.00 per hour

During March, the laboratory performed 2,000 core tests. On March 1 no direct materials (sand) were on hand. Variable manufacturing overhead is assigned to core tests on the basis of direct labour hours. The following events occurred during March:

8,600 pounds of sand were purchased at a cost of 7,310.

7,200 pounds of sand were used for core tests.

840 actual direct labour hours were worked at a cost of 8,610.

Actual variable manufacturing overhead incurred was 3,200.

The variable manufacturing overhead efficiency variance for March is:

Multiple Choice

  1. 320 unfavourable.
  2. 320 favourable.
  3. 360 unfavourable.
  4. 360 favourable.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cornerstones of Managerial Accounting

Authors: Maryanne Mowen, Don Hanson, Dan Heitger, David McConomy, Bradley Witt, Jeffrey Pittman

3rd Canadian edition

176530886, 176721231, 978-0176721237

More Books

Students also viewed these Accounting questions

Question

1 x > 0, f(1) = 9 X f'(x) = 16x + 4x + In( |x| ) + 5

Answered: 1 week ago

Question

Values: What is important to me?

Answered: 1 week ago

Question

Purpose: What do we seek to achieve with our behaviour?

Answered: 1 week ago

Question

An action plan is prepared.

Answered: 1 week ago