Question
1 Approved Answer
Crabe Company planned to use 1 yard of material per unit budgeted at $95 a yard. However, the material actually cost $93 per yard. The
Crabe Company planned to use 1 yard of material per unit budgeted at $95 a yard. However, the material actually cost $93 per yard. The company actually made 4400 units, although it had planned to make only 3800 units. Total yards used for production were 4530 . What is the total materials variance? $57000U$12350U$3290U$9060F Crabe Company planned to use 1 yard of material per unit budgeted at $95 a yard. However, the material actually cost $93 per yard. The company actually made 4400 units, although it had planned to make only 3800 units. Total yards used for production were 4530 . What is the total materials variance? $57000U$12350U$3290U$9060F
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started