Question
Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Production Activity Indirect
Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records.
Production Activity Indirect Labor Indirect Materials Other Overhead
Grinding $320,000
Polishing $135,000
Product modification 600,000
Providing power $255,000
System calibration 500,000
Additional information on the drivers for its production activities follows.
Grinding: 13,000 machine hours
Polishing: 13,000 machine hours
Product modification 1,500 engineering hours
Providing power 17,000 direct labor hours
System calibration 400 batches
- Classify each activity as unit level, batch level, product level, or facility level.
- Compute the activity overhead rates using ABC. Combine the grinding and polishing activities into a single cost pool.
- Determine the overhead costs to assign to the following jobs using ABC.
Job 3175: Job 4286:
Number of units 200 units 2,500 units
Machine hours 550 MH 5,500 MH
Engineering hours 26 eng. hours 32 eng. hours
Batches 30 batches 90 batches
Direct labor hours 500 DLH 4,375 DLH
- What is the overhead cost per unit for Job 3175? What is the overhead cost per unit for Job 4286?
- If the company uses plantwide overhead rate based on direct labor hours, what is the overhead cost for each unit of Job 3175? Of Job 4286?
- Compare the overhead costs per unit computed in requirements 4 and 5 for each job. Which method more accurately assigns overhead costs?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started