Crane company is constructing a building. Construction began on January 1 and was completed on December 31. expenditures were $64000000 on March 1, $5290000 on
Crane company is constructing a building. Construction began on January 1 and was completed on December 31. expenditures were $64000000 on March 1, $5290000 on June 1, and $8650000 on December 31. Cra...