Crane Company used high-low data from June and July to determine its variable cost of $10 per unit. Additional information follows: Month Units produced Total
Crane Company used high-low data from June and July to determine its variable cost of $10 per unit. Additional information follows: Month Units produced Total costs June 2300 $35000 July 1000 23000 If Cranes produces 2600 units in August, how much is its total cost expected to be?
$8364
$38000
$36000
$24000