Crane Construction Company began work on a $ 4 0 0 , 5 0 0 construction contract in 2 0 2 5 . During 2

Crane Construction Company began work on a $400,500 construction contract in 2025. During 2025, Crane incurred costs of $269,500, billed its customer for $230,500, and collected $179,000. At December 31,2025, the estimated additional costs to complete the project total $150,740.
Prepare Crane's journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the cost-recovery method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No entry" for the account titles and enter 0 for the amounts. Round answers to 0 decimal places, e.g.5,275. List all debit entries before credit entries. Do not round intermediate calculations.)
No. Account Titles and Explanation
Debit
(a)
Construction Expenses
Construction in Process
Revenue from Long-Term Contracts
(b) Loss from Long-Term Contracts
Credit
]
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

A Survey Of Financial And Managerial Accounting

Authors: Roger H. Hermanson, Roland F. Salmonson, James D. Edwards

5th Edition

ISBN: 025606976X, 978-0256069761

More Books

Students also viewed these Accounting questions