Crane Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price contract for $2.9 million beginning September 1, 2020, to

Crane Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price contract for $2.9 million beginning September 1, 2020, to build a road for a municipality. It has been estimated that the road construction will be complete by June 2022. The following data pertain to the construction period.

2020 2021 2022
Costs to date $848,000 $1,871,250 $2,428,000
Estimated costs to complete 1,802,000 623,750 0
Progress billings to date (non-refundable) 890,000 2,378,000 2,900,000
Cash collected to date 748,000 2,271,000 2,900,000

Using the percentage-of-completion method, calculate the estimated gross profit that would be recognized during each year of the construction period.

2020 2021 2022

Gross profit / (loss) $ $ $

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions