Crashing almost always accelerates the schedule while increasing project risk, whereas fast tracking almost always accelerates the
Fantastic news! We've Found the answer you've been seeking!
Question:
Crashing almost always accelerates the schedule while increasing project risk, whereas fast tracking almost always accelerates the schedule while increasing project cost.
a. True
b. False