Cray Computer Corporation is developing a new super computer. The table below lists the project activities. normal and crash times, and normal and crash

   

Cray Computer Corporation is developing a new super computer. The table below lists the project activities. normal and crash times, and normal and crash costs. Activity A Co De Description Design Evaluate equipment Write methods report Build prototype Write equipment report Test prototype Write final report Immediate Predecessor(s) F.F Time (weeks) Crash 10 Normal 342 6+ 74 302 442 Cost ($1.000) Normal Crash 200 200 80 100 500 80 125 20 140 45 170- 30- 160- 105 a. Draw an activity network diagram for this project. Using the normal activity times, determine the early start, early finish. late start, and late finish times for each activity. Record these values in the diagram.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

a Activity Network Diagram A 80 v v C 40 D 200 v v B 20 E 30 v v v F 105 G 45 v H 160 Early Start ES ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Accounting Information for Decision-Making and Strategy Execution

Authors: Anthony A. Atkinson, Robert S. Kaplan, Ella Mae Matsumura, S. Mark Young

6th Edition

137024975, 978-0137024971

More Books

Students also viewed these General Management questions

Question

Describe three forms of conflict from the work of Lewin.

Answered: 1 week ago

Question

Define deferred revenue. Why is it a liability?

Answered: 1 week ago

Question

Unequal status relationships lead to a stable society.

Answered: 1 week ago