Create a Network Diagram and Critical Path of the following Precedence table: Task ID WSB # Task Name Predecessor Duration (Days) 1 2.1.1 Research Online
Create a Network Diagram and Critical Path of the following Precedence table:
Task ID | WSB # | Task Name | Predecessor | Duration (Days) |
1 | 2.1.1 | Research Online Sales Platforms | None | 5 |
2 | 2.1.2 | Evaluate Storefront Locations | None | 5 |
3 | 2.1.3 | Decide on Sales Strategy (Online, Storefront, or Both) | 1,2 | 3 |
4 | 2.2.1 | Develop E-commerce Website | 3 | 10 |
5 | 2.2.2 | Design Storefront Layout | 3 | 7 |
6 | 2.2.3 | Implement Point of Sale (POS) System | 3 | 5 |
7 | 3.1.1 | Identify Staffing Needs | None | 4 |
8 | 3.1.2 | Develop Job Descriptions | 7 | 6 |
9 | 3.1.3 | Determine Hiring Timeline | 8 | 3 |
10 | 3.2.1 | Advertise Job Openings | 9 | 5 |
11 | 3.2.2 | Conduct Interviews | 9 | 8 |
12 | 3.2.3 | Select and Hire Bakers, Marketing Team, and Delivery Drivers | 11 | 10 |
13 | 3.3.1 | Develop Training Program | 12 | 7 |
14 | 3.3.2 | Onboard New Hires | 12,13 | 10 |
15 | 3.3.3 | Continuous Training for Skill Enhancement | 14 | 5 |
16 | 4.1.1 | Identify Required Bakery Equipment | None | 4 |
17 | 4.1.2 | Research and Select Suppliers | 16 | 6 |
18 | 4.1.3 | Procure and Install Equipment | 17 | 8 |
19 | 4.2.1 | Determine Ingredient Requirements | None | 5 |
20 | 4.2.2 | Establish Relationships with Suppliers | 19 | 7 |
21 | 4.2.3 | Set Up Raw Material Inventory System | 20 | 6 |
22 | 4.3.1 | Identify Additional Supplies (Packaging, Cleaning, etc.) | None | 4 |
23 | 4.3.2 | Source and Procure Additional Supplies | 22 | 7 |
24 | 4.3.3 | Manage Inventory for Other Supplies | 23 | 6 |
25 | 5.1.1 | Conceptualize Bakery Product Ideas | None | 5 |
26 | 5.1.2 | Develop Initial Prototypes | 25 | 8 |
27 | 5.1.3 | Test Prototypes for Quality and Taste | 26 | 6 |
28 | 5.2.1 | Conduct Market Testing | 27 | 10 |
29 | 5.2.2 | Gather Feedback and Make Improvements | 28 | 7 |
30 | 5.2.3 | Finalize Recipes and Production Processes | 29 | 6 |
31 | 5.3.1 | Develop Commercialization Strategy | None | 5 |
32 | 5.3.2 | Launch Products in the Market | 31 | 7 |
33 | 5.3.3 | Monitor Initial Market Response and Adjust as Needed | 32 | 5 |
34 | 6.1.1 | Analyze Market and Identify Target Customer Segments | None | 6 |
35 | 6.1.2 | Develop Customer Profiles | 34 | 5 |
36 | 6.1.3 | Refine Marketing Strategy Based on Segmentation | 35 | 4 |
37 | 6.2.1 | Choose Marketing Channels (Social Media, Print, Influencers) | 36 | 7 |
38 | 6.2.2 | Develop Marketing Materials | 37 | 8 |
39 | 6.2.3 | Execute Marketing Campaigns and Monitor Performance | 38 | 10 |
40 | 6.3.1 | Develop Bakery Branding (Logo, Packaging, etc.) | None | 6 |
41 | 6.3.2 | Establish Brand Guidelines | 40 | 5 |
42 | 6.3.3 | Implement Branding Across all Touchpoints | 41 | 8 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started